Project: Bradford District Heating Network, Bradford
Client: ThermaMech
Role: Cx Management
Project Overview
Cleartech was involved in the commissioning management of a major district heating network project in Bradford, working alongside ThermaMech.
The project centred around an Energy Centre designed to supply heat to multiple buildings throughout the city, including Bradford City Hall and the University. The network brings heat generation together at a central location, distributing it to connected buildings through an extensive network of pipework.
ThermaMech was responsible for installing the plant within the Energy Centre, including large-scale equipment such as boilers and pumps, as well as the associated pipework throughout the network. Its subcontractors undertook the testing and commissioning of the associated plant.
Cleartech provided Cx Management support, bringing together the expectations and requirements of the Council, University, design teams and ThermaMech. This helped ensure all parties were working towards a shared goal: delivering an operational district heating network on time.
Scope of Works
Cleartech’s Cx Management involvement focused on coordinating the commissioning process, supporting communication across the project team and helping ensure the work aligned with the client’s requirements.
The scope included:
- Project Coordination: Bringing together the expectations and requirements of the Council, University, design teams and ThermaMech to support a coordinated approach to commissioning.
- Commissioning Tracker: Creating a project-specific commissioning tracker to monitor and manage commissioning activities and progress.
- Documentation Review: Reviewing project documentation to help ensure the relevant information and requirements were captured ahead of testing.
- Test Script Development: Preparing test scripts aligned with the client’s project specification, providing a clear framework for the testing process.
- Testing Coordination: Carrying out testing of the prepared scripts alongside the client, supporting the review of the required testing procedures.
- Commissioning Management: Supporting the coordination and management of commissioning activities across the project, helping keep the different parties aligned with the requirements and delivery objectives.
Project Outcome
The district heating network is now operational and supplying heat to connected buildings across Bradford.
With heat generated centrally at the Energy Centre and distributed through the network, the original heat-generating plant within the connected buildings has been removed.
Cleartech is proud to have supported ThermaMech on this significant infrastructure project. Through Cx Management, Cleartech helped bring the different project parties together, coordinate commissioning requirements and support the delivery of an operational district heating network.