Service: HVAC Commissioning & Water Treatment
Project: Kirkintilloch Town Hall
Client: Marmac Services
Cleartech Group Ltd were engaged by Marmac Services to carry out HVAC commissioning & water treatment services at the newly-renovated Kirkintilloch Town Hall. The restoration and extension works is an exciting £5m project, carried out in order to accommodate a more flexible and contemporary space that will host events such as; weddings, performances, heritage displays, receptions and meetings. The extension will allow the town hall to be more accessible and will provide office accommodation on the first floor.
The project has recently been nominated for two Scottish Property Awards in the Architectural Excellence (Public Use) and Town Centre Regeneration Project of the Year categories. Well done to all of the teams involved – we’re glad to have played a part in such an innovative build.
Project Overview
Scope of Works:
- Domestic Water Services Chlorination
- Potable Water Samples Taken
- Water Sample Analysis
- Chemical Cleaning to BSRIA BG 29/2012
- Water and Ventilation Balancing of Systems as given in client enquiry
Cleartech’s Approach
Our domestic water services chlorination include cleaning and chlorinating all associated installation hot and cold water services to BS8558. Our team of highly qualified engineers also took potable water samples from the systems, which were then taken and tested at a UKAS accredited laboratory – with results issued directly to the client.
Our scope of works also included carrying out a full pre-commission chemical clean, static flushing, dynamic flushing and dosing of corrosion inhibitor – all of which were conducted in accordance with BSRIA BG 29/2012 Pre-commissioning Cleaning of Pipework Systems. HVAC commissioning works included water and ventilation balancing of systems, as instructed by the client, and carried out as per C.I.B.S.E code ‘A’ and ‘W’.
Cleartech invest considerable time, effort and resources on building the expertise of our engineers and ensuring that all works are completed correctly and to the required specification.
For further information or advice on HVAC commissioning and water treatment, or for a quote, call today on 01698 682000, send an email to [email protected] or submit a contact form on our website.