Cleartech were engaged by Castle Building Services to carry out the HVAC commissioning and water treatment at the new Quay Zone site in Girvan. Operated by South Carrick Community Leisure on behalf of South Ayrshire Council, the newly built facility accommodates a 25-metre swimming pool, soft play area, fitness gym and multi-purpose studio. Opening in April of 2017, the long-awaited sports hub will bring a town pool back in to Girvan, after many residents complained about its absence. Not only is the pool back, but it now looks on to sites of Ailsa Craig.

HVAC Commissioning

 

 

 

 

 

 

 

 

Project Overview

Scope of Works:

  • Cleaning & chlorination of new installation hot & cold water services
  • Potable water samples tested at UKAS laboratory
  • Full pre-commission chemical clean, static flushing, biocide wash & dynamic flushing
  • Dosing of corrosion inhibitor
  • Water & ventilation balancing of systems, complete with final report

 

Cleartech’s Approach

Our full scope of works included cleaning and chlorination of new installation hot and cold water services to BS8558   Specification at the Quay Zone. Multiple potable water    samples were taken and tested at a UKAS accredited lab and results were issued to our client. We also carried out a full pre-commission chemical clean, static flushing, biocide wash, dynamic flushing and dosing of  corrosion inhibitor  fully in accordance with BSRIA BG 29/2012 Pre-commission Cleaning of Pipework Systems. The estimated water content of the LTHW heating installation at the leisure centre was 5,200 litres.

Our HVAC commissioning works included carrying out water and ventilation balancing of systems as dictated by the    project specification. All works were carried out as per C.I.B.S.E code ‘A’ and ‘W’, complete with final report. The systems comprised of pumps, commissioning sets, AHUs, HRUs, Ex fans, FCUs, FCU S Grilles, S grilles & Ex grilles. Cleartech invest considerable time, effort and resources in developing the expertise of our engineers and ensuring that all work is completed fully within regulation guidelines. If you have a project which requires our services then contact us today.