Blackrock Edinburgh | Commissioning Management

Project – Blackrock, Edinburgh

Client – FES (M&E Contractor)

Role – MEP Commissioning Manager

Project Overview

The Blackrock office redevelopment, Edinburgh, was a high-spec refurbishment of an existing building, with new installation and commissioning of all MEP and life safety systems, including a standby generator. Cleartech were appointed in the role of commissioning manager for M&E contractor FES, covering all commissioning activities throughout the project.

Scope of Works

Cleartech’s commissioning management scope on this project covered the following:

  • Commissioning Tracker: Developed and maintained a live commissioning tracker throughout the project to monitor progress, manage system readiness, and ensure timely close-out of all activities, which was shared with the Main Contractors commissioning manager on a weekly basis.
  • Commissioning Meetings: Chaired and coordinated weekly commissioning meetings with the M&E team to align activities, track progress, and resolve issues.
    • Collate and issue the meeting minutes.
    • Attended weekly commissioning meetings with the Main Contractors commissioning manager to report progress
  • Collate, review and issue all testing and commissioning paperwork
  • Witness Testing and offer up tests for witnessing to main contractor and clients commissioning team, List of associate systems below:
    • HVAC systems (Ventilation, LTHW,CHW, VRF)
    • Smoke extract systems
    • Electrical distribution systems
    • Domestic water and drainage services
    • Fire and life safety systems
    • Building Management System (BMS) interface testing
    • Security Systems (CCTV and Access control)
    • Fire damper drop tests across the project to verify safety system performance and compliance.
    • Generator load testing
    • Critical data rooms heat load testing
    • IST testing
    • Collate data and issue final generator load and critical data rooms heat load testing

Cleartech followed a structured, phased approach to ensure effective commissioning delivery:

Construction Stage:

  • Developed the project-specific Commissioning Plan and Tracker.
  • Reviewed M&E install to ensure system readiness.
  • Chaired weekly commissioning coordination meetings for duration of the project to address progress, risks, and dependencies.

Testing and Commissioning Stage:

  • Witnessed pre-commissioning activities (pressure testing etc) and functional performance testing of all MEP systems.
  • Verified system performance against design intent and specification requirements.
  • Recorded observations, results, and corrective actions in the commissioning tracker.
  • Issued weekly 2 week witnessing lookahead to main contractor and clients commissioning team

Handover Stage:

  • Ensured all testing documentation and commissioning certificates were complete and compliant.
  • Provided commissioning input into final handover documentation for client acceptance.
  • Assisted with client demonstrations and training